From: Charles Baker
Sent: Wednesday, May 30, 2007 6:05 AM
To: Eric Braun, St. Louis County
Cc: Mike at Gateway; Eric Hogan at Focal Pointe
Subject: Tilles Park project site review update 5.29.07
Eric,
As representative of our product StabiliGrid, it is my job to site-supervise and advise on the application of our grid products for your project at Tilles Park.
Site review summary: 5/30/07:
I arrived at the job site about 7am. It was raining lightly, but graduated into moderate rainfall until about 11am. After that, light showers, until sun breaks around 3 pm.
Finish grading of the leveling layer for the StabiliGrid areas continued and was completed about 2:30 pm.
Final grade analysis determined about 6 large area “soft spots”, some with surface water present.
It was determined that the StabiliGrid installation could continue, under the following conditions:
1) That no vehicular traffic is allowed onto the grid installation area, either prior to or after the StabiliGrid application, until the site conditions improved and the soft spots are no longer evident. These “soft spots” were marked with orange paint, and can be seen through the grid cells. Settling could occur, which would require the grid area be disassembled, the leveling layer amended as required, and then the StabiliGrid re-installed. It is recommended that the StabiliGrid cells not be filled until the sub-grade saturation has stabilized.
2) That prior to the soil filling of the StabiliGrid, someone in authority from St. Louis County Parks reviews the site, and approves the grading and contours now prevalent to the grid installation areas.
3) That soil filling/hydro-seeding take place only after mutual agreement and acceptance of the sub-grade condition, by representatives of St Louis County Parks, Gateway Contractors, and Focal Point.
4) That the StabiliGrid installation area is adequately secured from vehicular traffic until such time the area is mutually released to service by St Louis County Parks, Gateway Contractors, and Focal Point.
Lay-out and Installation of the StabiliGrid in the center section began about 2:30 pm, and by 4:30 pm approximately 1200 sq. ft. had been installed.
Plans for tomorrow include the near completion of the center section, as well as the lay-out and beginning of installation on the outer section.
Weather forecast for tomorrow is 60% chance of rain. The amount of rain will determine if, and how much, of the installation will be evident by days end.
I will be leaving the job-site approx. 12 pm tomorrow to begin my return to Seattle. It would be my pleasure to discuss this project with anyone who wishes to do so, prior to 12 pm.
Regards,
Charles Baker, President
Eco-Terr Distributing Inc.
425 864-1701
|